Just signed with a GC – first big renovation. When do I need to order cabinets? When do I order appliances?
I know I'm supposed to be excited. We just signed the contract. We celebrated with champagne. But now, at 2 a.m., I'm lying awake staring at the ceiling, mentally replaying every warning I've ever heard about renovation delays.
Here's where we are: signed yesterday. Demo starts in four weeks. The GC handed me a one-page schedule that basically says "week 1–2 demo, week 3–4 rough-in, week 5–8 finish" — and when I asked for more detail, he smiled and said "don't worry, we'll let you know what you need when you need it."
That is not the answer I needed. I'm not a professional. I don't know what "when you need it" means in actual calendar days, and I've already heard enough horror stories from friends to know that "don't worry" is exactly the phrase people say right before something goes very, very wrong.
Here's what I'm trying to wrap my head around:

I've got quotes from three different cabinet shops:
Shop A (big-box custom, semi-custom): 8–10 weeks, but limited wood options
Shop B (local custom, fully bespoke): 14–16 weeks, beautiful work, I've seen it in person
Shop C (online RTA, "ready to assemble"): ships in 4 weeks, but I have to assemble it myself
The GC strongly prefers Shop B because he's worked with them before. I love their work. But 14 weeks from when? If I order today, they arrive while the GC is still doing rough-in. If I wait two weeks — which is what my GC suggested — then they don't arrive until week 16, which means the whole job stalls.
And that's just cabinets. What about appliances? I want a 36-inch gas range with a griddle. The showroom said "6 to 12 weeks depending on the brand." Six or twelve — that's a huge difference. The fridge I want comes in 3 weeks, but the panel-ready dishwasher I like is backordered until... they don't even know.
Tile? We found a beautiful handmade zellige tile from a local importer. She said "usually in stock, but sometimes it's 4–6 weeks if we need to bring a shipment in." How do I plan for "sometimes"?
Windows? We're replacing three old single-pane windows in the kitchen. That's a separate sub-contractor. The GC said "2–3 weeks" but then I read online that custom window sizes are actually 6–8 weeks. I measured the openings myself last night — I think they're standard sizes, but I'm not 100% sure.
Lighting? I have a Pinterest board of pendant lights. I haven't even sent it to anyone. Do I need to buy those now? Can they be installed later? I genuinely don't know.
But I don't know how to translate this into a real schedule. Do I order everything now and risk having boxes everywhere for months? Or do I stagger it — and risk the one long-lead item holding up the whole project?
The GC gave me a schedule that looks something like this (paraphrased):
Week 0 (now): Signed contract. "Start shopping."
Week 1–2: Demolition. "Let us know if you find anything weird."
Week 3–4: Rough-in plumbing, electrical, HVAC. "Have your fixtures ready."
Week 5–6: Insulation, drywall. "We'll let you know about paint colors later."
Week 7–8: Cabinets install. "They should be here by then."
Week 9–10: Countertops templated and installed.
Week 11–12: Flooring, backsplash, trim.
Week 13–14: Finishing touches, punch list.
The problem is, when I asked the GC "What happens in week 7 if the cabinets aren't here?" he just said "we'll work around it." That doesn't fill me with confidence. I don't want to work around it. I want the cabinets to show up on time.
So I need real answers from people who have actually done this.

I'm not looking for generic advice. I'm looking for your timeline, your mistakes, your one piece of hard-won wisdom.
Specifically:
Cabinets: What week did you order them relative to demo? If you ordered before demo, did the GC get annoyed? If you ordered after demo, did you regret it?
Appliances: What appliance took way longer than expected? Did you end up buying something you didn't want just to keep the job moving? Or did you wait and let the job stall?
Tile/flooring: Did you have it sitting in your garage for months? How much space did it take up? Did it get damaged?
Windows: If you replaced windows, did you confirm the size yourself or trust the contractor? Any horror stories about wrong measurements?
What did you order too late and regret? I want to hear the ugly ones — the ones where you lost weeks because you didn't know you should have ordered something earlier.
What did you order too early and ended up storing for months? And how did that go?
The bigger question: How much did you actually rely on your GC to tell you when to order things — and how much did you have to figure out yourself? Because right now I feel like I'm in that awkward middle zone where the GC says "trust me" and my friends say "trust no one."
And the big one — the one I keep coming back to:
If you could go back to the day you signed your contract — before demo, before any ordering, before anything — and give your past self a single piece of advice about ordering timing... what would it be?
One thing. Not a list. Not "be organized." One specific, concrete, actionable thing you'd tell yourself to order earlier (or later) that would have saved you real, measurable pain.
I realize this is a very beginner question. I'm not pretending otherwise. But I genuinely believe that every renovation starts with this exact moment of confusion — the moment where you realize that a one-page schedule from a GC is not a plan, it's a suggestion. And I'm hoping that by collecting your stories, I can build myself a better plan.
So please — tell me your timeline. Tell me your mistakes. Tell me what you'd do differently. I'm taking notes, I'm reading everything, and I promise I'll pay it forward when I'm the one answering this question for someone else in a few years.
And if nothing else, tell me I'm not alone in feeling completely overwhelmed by this "when do I order anything" question. Because right now, it's 2:30 a.m., and I'm making spreadsheets instead of sleeping, and I have a feeling I'm not the first person to do this.